T
tedbellinger
I am looking for tips on how best to set up and manage projects that include
subcontractors. Typically these subcontracts are fixed price, with progress
payments linked to milestones, and I need to be able to plan my oversight
work as well as manage task dependencies that impact the project schedule. I
don't typically have any visibility of the sub's personnel resources nor of
the sub's estimates of the hours required to do the work. I just know that
they must perform certain tasks as part of their subcontract, and that these
tasks must be completed for them to get the progress payment.
Are there common approaches to projects with subs? Are there things to
watch out for when setting up such a project? I suspect I am making my
project plans more complicated and less accurate than I could if I did it
right.
BTW, I am using Project Professional 2003.
subcontractors. Typically these subcontracts are fixed price, with progress
payments linked to milestones, and I need to be able to plan my oversight
work as well as manage task dependencies that impact the project schedule. I
don't typically have any visibility of the sub's personnel resources nor of
the sub's estimates of the hours required to do the work. I just know that
they must perform certain tasks as part of their subcontract, and that these
tasks must be completed for them to get the progress payment.
Are there common approaches to projects with subs? Are there things to
watch out for when setting up such a project? I suspect I am making my
project plans more complicated and less accurate than I could if I did it
right.
BTW, I am using Project Professional 2003.