The Gantt View shows us a project's progress to it's date, so that the
percentage complete has a date that matches it along the timeline. This
shows us who's late and who's not. Is this viewable, manageable anywhere
else? Ie. The 'CompleteThrough' field
 
D

Dale Howard [MVP]

Ryan --

You can see the same information by inserting the Resume field in either the
Task Usage or Resource Usage views. Hope this helps.
 