Mandays

L

LemonWithMint

Hi

In MS Project, to change the scheduling options for a project, we go to
Tools -->Options -->Schedule --> Scheduling option for Project Name,

and then we change the settings as we want. For example, to present works in
days instead of hours, we set Days in [Work is entered in:] dropdown list.
But how can we do that in Project Server?

We use mandays, and we need the views in project center and project details
to show work in days instead of hours, can you help me please?

Thank you
 
P

Paul Conroy

You can change the reporting units in the timesheet from hours to days and
then import the timesheet data into task updates

server settings>Timesheet Settings & Defaults>Default Reporting Units

With the tracking method set to "Actual work done and work remaining", you
are presented with work planned in days and the amount of effort spent can be
entered in days. However you don't get a timephased entry table as you do
when reporting using "Hours of work done per period"

--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com
 
L

LemonWithMint

Thank you Paul, appreciating your help

Executives want to see "Days" instead of "Hours" in the Work field for all
the available views.

I tried your suggestion but still "Hours" appear in the Work field. are you
sure this will address our requirement here?

Thank you,

Paul Conroy said:
You can change the reporting units in the timesheet from hours to days and
then import the timesheet data into task updates

server settings>Timesheet Settings & Defaults>Default Reporting Units

With the tracking method set to "Actual work done and work remaining", you
are presented with work planned in days and the amount of effort spent can be
entered in days. However you don't get a timephased entry table as you do
when reporting using "Hours of work done per period"

--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com


LemonWithMint said:
Hi

In MS Project, to change the scheduling options for a project, we go to
Tools -->Options -->Schedule --> Scheduling option for Project Name,

and then we change the settings as we want. For example, to present works in
days instead of hours, we set Days in [Work is entered in:] dropdown list.
But how can we do that in Project Server?

We use mandays, and we need the views in project center and project details
to show work in days instead of hours, can you help me please?

Thank you
 
P

Paul Conroy

No it won't.

You could however create a custom field to recalculate work to days and show
this column instead of the work column.

Paul
--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com


LemonWithMint said:
Thank you Paul, appreciating your help

Executives want to see "Days" instead of "Hours" in the Work field for all
the available views.

I tried your suggestion but still "Hours" appear in the Work field. are you
sure this will address our requirement here?

Thank you,

Paul Conroy said:
You can change the reporting units in the timesheet from hours to days and
then import the timesheet data into task updates

server settings>Timesheet Settings & Defaults>Default Reporting Units

With the tracking method set to "Actual work done and work remaining", you
are presented with work planned in days and the amount of effort spent can be
entered in days. However you don't get a timephased entry table as you do
when reporting using "Hours of work done per period"

--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com


LemonWithMint said:
Hi

In MS Project, to change the scheduling options for a project, we go to
Tools -->Options -->Schedule --> Scheduling option for Project Name,

and then we change the settings as we want. For example, to present works in
days instead of hours, we set Days in [Work is entered in:] dropdown list.
But how can we do that in Project Server?

We use mandays, and we need the views in project center and project details
to show work in days instead of hours, can you help me please?

Thank you
 
L

LemonWithMint

Thank you again Paul

You are right; this might be a possible workaround. Do you know other
alternatives?


Paul Conroy said:
No it won't.

You could however create a custom field to recalculate work to days and show
this column instead of the work column.

Paul
--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com


LemonWithMint said:
Thank you Paul, appreciating your help

Executives want to see "Days" instead of "Hours" in the Work field for all
the available views.

I tried your suggestion but still "Hours" appear in the Work field. are you
sure this will address our requirement here?

Thank you,

Paul Conroy said:
You can change the reporting units in the timesheet from hours to days and
then import the timesheet data into task updates

server settings>Timesheet Settings & Defaults>Default Reporting Units

With the tracking method set to "Actual work done and work remaining", you
are presented with work planned in days and the amount of effort spent can be
entered in days. However you don't get a timephased entry table as you do
when reporting using "Hours of work done per period"

--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com


:

Hi

In MS Project, to change the scheduling options for a project, we go to
Tools -->Options -->Schedule --> Scheduling option for Project Name,

and then we change the settings as we want. For example, to present works in
days instead of hours, we set Days in [Work is entered in:] dropdown list.
But how can we do that in Project Server?

We use mandays, and we need the views in project center and project details
to show work in days instead of hours, can you help me please?

Thank you
 
P

Paul Conroy

sorry no.

--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com


LemonWithMint said:
Thank you again Paul

You are right; this might be a possible workaround. Do you know other
alternatives?


Paul Conroy said:
No it won't.

You could however create a custom field to recalculate work to days and show
this column instead of the work column.

Paul
--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com


LemonWithMint said:
Thank you Paul, appreciating your help

Executives want to see "Days" instead of "Hours" in the Work field for all
the available views.

I tried your suggestion but still "Hours" appear in the Work field. are you
sure this will address our requirement here?

Thank you,

:

You can change the reporting units in the timesheet from hours to days and
then import the timesheet data into task updates

server settings>Timesheet Settings & Defaults>Default Reporting Units

With the tracking method set to "Actual work done and work remaining", you
are presented with work planned in days and the amount of effort spent can be
entered in days. However you don't get a timephased entry table as you do
when reporting using "Hours of work done per period"

--
Did this post help you. Consider passing on the good will by making a
donation this great charity.
http://www.fundraiseonline.co.nz/TheProjectServerGuru/

http://theprojectserverguru.spaces.live.com


:

Hi

In MS Project, to change the scheduling options for a project, we go to
Tools -->Options -->Schedule --> Scheduling option for Project Name,

and then we change the settings as we want. For example, to present works in
days instead of hours, we set Days in [Work is entered in:] dropdown list.
But how can we do that in Project Server?

We use mandays, and we need the views in project center and project details
to show work in days instead of hours, can you help me please?

Thank you
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top