Hi
In MS Project, to change the scheduling options for a project, we go to
Tools -->Options -->Schedule --> Scheduling option for Project Name,
and then we change the settings as we want. For example, to present works in
days instead of hours, we set Days in [Work is entered in:] dropdown list.
But how can we do that in Project Server?
We use mandays, and we need the views in project center and project details
to show work in days instead of hours, can you help me please?
Thank you