I have an issue where a PM goes into MS Project Pro and updates a task to
100%, if a resource assigned to that task later submits a % complete, that
task changes back from 100%. Is this expected behavior and what are the
workarounds?

Grant
 
R

Rod Gill

The manager and the resource can't both be correct. By default the resource
is having the last say because they are saying there is more work to be
done. The task cannot therefore be complete. I don't think you want to do
anything different? I would educate project managers in making more precise
task descriptions so it's easier to define when they are complete and
educate resources in the standards you need for updating tasks.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.project-systems.co.nz/
Email rodg AT project-systems DOT co DOT nz
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top