Manually allocating time over several months

R

Roger

Hi,
As part of some resource plannig we're doing, I'd like to be able to
manually allocate effort to resources over the following few months.

For example, ResourceA will have 21 days assigned to TaskA, and I want him
to be assigned for 5 days in the first month, 4 days in the second month, 10
days in the third month and 2 days in the fourth month. I can't for the life
of me figure out how to do this in Project, alothugh I recall being able to
do this in ABT's (now Niku's) PMW/Workbench.

Thanks in advance for any help!
Roger
 
R

Roger

Oh.. that's embarrassingly easy.

Thanks very much!

<Reminder to self - explore more views>

Regards,
Roger
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top