Hi,
As part of some resource plannig we're doing, I'd like to be able to
manually allocate effort to resources over the following few months.
For example, ResourceA will have 21 days assigned to TaskA, and I want him
to be assigned for 5 days in the first month, 4 days in the second month, 10
days in the third month and 2 days in the fourth month. I can't for the life
of me figure out how to do this in Project, alothugh I recall being able to
do this in ABT's (now Niku's) PMW/Workbench.
Thanks in advance for any help!
Roger
As part of some resource plannig we're doing, I'd like to be able to
manually allocate effort to resources over the following few months.
For example, ResourceA will have 21 days assigned to TaskA, and I want him
to be assigned for 5 days in the first month, 4 days in the second month, 10
days in the third month and 2 days in the fourth month. I can't for the life
of me figure out how to do this in Project, alothugh I recall being able to
do this in ABT's (now Niku's) PMW/Workbench.
Thanks in advance for any help!
Roger