When I set the Work to 0, then the task is marked as milestone. Is that a
bug and how can I fix that?

Many thanks,

Joerg
 
G

Gary L. Chefetz [MVP]

Joerg:

If you don't want it to be a milestone, set the duration to a value greater
than zero.
 