Marking a Milestone 100% Complete via PWA

J

Jeremy Jensen

Anyone know how to mark a Milestone 100% complete via PWA? I tried simply
entering 0 hrs into Actual Work column in the tasks view, but after the PM
accepted the task update it still said 0% complete in Project Professional
2003.
 
E

Earl Lewis

Jeremy,

Set Remaining Work to 0 and Actual Work to the number of hours actually spent, assuming you're using hours work tracking.

Do you know what tracking setting is being used for your installation?

Earl
Anyone know how to mark a Milestone 100% complete via PWA? I tried simply
entering 0 hrs into Actual Work column in the tasks view, but after the PM
accepted the task update it still said 0% complete in Project Professional
2003.
 
J

Jeremy Jensen

OK. I'll try that. I entered 0 for remaining work and 0 for actual work.

We're using hours in PWA, not percent complete.

Thanks for your help.

Jeremy
 
E

Earl Lewis

Jeremy,

Sorry. I didn't read your post carefully enough. I see now that you're troubled by milestones, not regular tasks. I'll have to check into this.

Earl
Jeremy,

Set Remaining Work to 0 and Actual Work to the number of hours actually spent, assuming you're using hours work tracking.

Do you know what tracking setting is being used for your installation?

Earl
Anyone know how to mark a Milestone 100% complete via PWA? I tried simply
entering 0 hrs into Actual Work column in the tasks view, but after the PM
accepted the task update it still said 0% complete in Project Professional
2003.
 
J

Jeremy Jensen

OK. Thanks.

Earl Lewis said:
Jeremy,

Sorry. I didn't read your post carefully enough. I see now that you're troubled by milestones, not regular tasks. I'll have to check into this.

Earl

Jeremy,

Set Remaining Work to 0 and Actual Work to the number of hours actually spent, assuming you're using hours work tracking.

Do you know what tracking setting is being used for your installation?

Earl

Anyone know how to mark a Milestone 100% complete via PWA? I tried simply
entering 0 hrs into Actual Work column in the tasks view, but after the PM
accepted the task update it still said 0% complete in Project Professional
2003.
 
D

Dale Howard [MVP]

Jeremy --

The only way to do this from within PWA is to assign yourself to a small
token amount of work on the milestone task, such as 1 hour of Work. Then
enter 1 hour of Actual Work on the day the milestone was actually achieved.
Hope this helps.
 
J

John Bachelor

We just fixed this problem by installing SP1 for MS Project Pro.
There is a chance that SP1 does not fix the problem, if this happens apply
hot fix 891648 (SP1 must be on before you apply the hot fix).
 