Dear MPP users,
I have this scenario.
Task A: Assigned to resource R1, H1 hours of actual effort spent. H2
'remaining work' left to complete.
R1 is now leaving the organization, and the H2 hours need to be assigned to
a new resource R2. How do I indicate that in the MPP?
Do I assign R2 to task A, reduce the 'remaining work' of R1 to zero and then
move the hours to R2 and then do resource leveling?
How do I indicate to the MPP that R1 is no longer available.
Thanks,
Prashanth