J
John
All,
I have a project which I snapped a baseline. This project included some
tasks that I thought would need to be performed. However, those tasks do
not need to be performed. Using the Tracking Table and the Percent
complete/Hours Remaining fields, I know there is a way to represent those
tasks as completed - but not performed. Can someone tell me how? If not
the fields I mentioned, any other recommended method is helpful.
Thanks
John
I have a project which I snapped a baseline. This project included some
tasks that I thought would need to be performed. However, those tasks do
not need to be performed. Using the Tracking Table and the Percent
complete/Hours Remaining fields, I know there is a way to represent those
tasks as completed - but not performed. Can someone tell me how? If not
the fields I mentioned, any other recommended method is helpful.
Thanks
John