mass change of task start dates

J

Julie

Can anyone tell me if there is a way to take an existing project and move all the tasks to a new start date
 
M

Mike Glen

Hi Julie,

You didn't say which version you have, but for early versions,
Tools/Macro/Macros..., and in later versions on the Analysis toolbar, and
select the Adjust_Dates macro.

Welcome to this Microsoft Project newsgroup :)



FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on:)

Mike Glen
MS Project MVP

Julie said:
Can anyone tell me if there is a way to take an existing project and move
all the tasks to a new start date?
 
J

Julie

Hi Mike,
Thanks for the help - I have Project 98-SR-1.
I will let you know how I get on.
Thanks.
 
J

Julie

Hi Mike,
I cannot find the macro to adjust the dates. Is this a standard macro or where can I get it
Thanks.
 
J

Julie

Hi Mike

never mind - my GLOBAL.MPT file was corrupt so I could not see any macros
I fixed it and have successfully changed the dates
Thanks a million for the tip.
 