mass resource replacment due to chenging assignment owner

H

hanni

Hi,

when I change assignment owner is affects the task only after I go
into the task and rechoose the resource.
How can I do it at one time? I need to change more than 150 tasks (few
resources have changed the resource assignment owner)

Thanks,
Hanni
 
B

Barbara - Austria

Hello,

only an idea:
Switch to view "Resource: Usage". Insert Column "Assignment Owner". Change
assignment owner for the first task of the resource and pull down to change
the others.

Barbara
 
H

hanni

Hi,

Thanks for the idea but, Assignment Owner in the REsource Usage view
in open only for view. it cannot be changed thru this view.
 
B

Barbara - Austria

Hi,

sorry. I have checked it before writing, it worked for me. I am working with
admin permissions.

One additional idea: I can only select from existing assignment owners. So
if I need a new one I have to change the standard assignment owner for this
resource first in resource center. After re-opening project the new
assignment owner shows up in the pull down list.

Good luck!
 
D

Dale Howard [MVP]

Hanni --

I'm trying to figure out what you are attempting to do. Which of the
following do you want to accomplish:

(A) Resource A is assigned to the tasks, and Assistant A is the Assignment
Owner. This means that Assistant A will fill out and submit the task
progress for Resource A. You need to change Assistant A to Assistant B.

(B) Resource A is assigned to the tasks and you need to assign Resource B
to the tasks instead.

If your answer is (B) above, then refer to the following FAQ:

http://www.projectserverexperts.com/ProjectServerFAQKnowledgeBase/ReassignTasks.aspx

If the answer is (A), let us know.
 
H

hanni

My answer would probably be B but
and I'll explain:
I have resource A on a task and resource B is the resource assignment.
now, I have changed IN THE SERVER the resource assignment owner of A
to itself (why? because he took the reporters training so he can now
starts reporting on himself)
now, the resource owner have changed in the server but i dont see it
in the work plan.
the only thing that cause the resource assignment owner to be updated
is if I go into the task -> resources tab -> open the manu and click
again on the same name.
it is very hard and long to do it to all the tasks.
 
M

Mike Mahoney

hanni --

If you are simply trying to reassign tasks to Resource B that are currently
assigned to Resource A, then click Tools - Build Team from Enterprise and
make the change there.  If Resource A has done work on some of the tasks,
refer to the following FAQ:

http://www.projectserverexperts.com/ProjectServerFAQKnowledgeBase/Rea...

Hope this helps.








- Show quoted text -

Hannin
.
Check that you have applied service packs - if so should be able to
change the assignment owner in usage view as Barbara described.

regards

Mike
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top