Mass update to Resource Allocation

J

Joe

I have a plan with thousands of task items and about 20 resources. I have
already started tracking the plan. We are about 230% through, and Mgmt
decided to reduce the allocation of some of the resources to 80% allocation.
Is there an easy way to update the allocation for the remaining task items
for some of the resources? I don't want to change the calendar working hours
because they still work 8 hours a day, just mot 100% to the task in the plan.
Any ideas?

Thanks
 
J

Jan De Messemaeker

Hi,

Select the remaining tasks
Click the resource allocation button
Select the resource you want to change
Click replace
Select the same resoruce but add 80%
HTH
 