C
Carl Sprake, Oxford, UK
Please could you comment on the following scenario:
We currently have a single project plan, with about 1000 lines. This is
really a programme of interdependent projects.
We would like to split this file into one master project and about 12 sub
projects.
I appreciate that this will mean cutting out the twelve sub projects into
separate files and then re-inserting them as sub projects and re establishing
the dependencies.
However this should mean that team members and project managers for the sub
projects can then open only the project they are interested in, while the
programme manager can view the master project and all sub projects.
Only the master project will be published and all changes will be updated by
publishing the master project only. In addition, only the programme manager
has permission to make changes and publish updates.
Any comments or suggestions on how to better achieve this would be greatly
appreciated.
Thanks
We currently have a single project plan, with about 1000 lines. This is
really a programme of interdependent projects.
We would like to split this file into one master project and about 12 sub
projects.
I appreciate that this will mean cutting out the twelve sub projects into
separate files and then re-inserting them as sub projects and re establishing
the dependencies.
However this should mean that team members and project managers for the sub
projects can then open only the project they are interested in, while the
programme manager can view the master project and all sub projects.
Only the master project will be published and all changes will be updated by
publishing the master project only. In addition, only the programme manager
has permission to make changes and publish updates.
Any comments or suggestions on how to better achieve this would be greatly
appreciated.
Thanks