Jack Ferraro PMP
Hi,
I have 5 plans that share a common resource pool through share resource
options. These 5 plans are linked into a master plan to get a roll up of
milestones and a aggregrate view of resource utlizations. However, when I
view the details of the resource usage tasks under each resource name, I see
that numerous tasks are repeated causing the resource to appear
overallocated. I am running MS Project 2002. Any help would be appreciated