R
Roger
Hi all
A master milestone plan showing project status of 25 projects handled
by 12 PM's is being used at work.
The existing process is to have each PM update a separate MS Project
file "Master Milestone Plan" (or MMP for short). A time consuming and
unwieldy process as the same information is being entered in two
different locations by 12 PM's.
The solution seems to be to create the MMP, then on a weekly basis,
insert the latest copy of the sub projects (25 of) into the MMP.
1. Is this a good procedure?
2. What is the impact of PM's using different calendars?
3. If projects are baselined, what impact on the MMP will be made?
4. If changes are made in the MMP - what if scenarios for example, the
sub projects will be affected. How can this be managed?
Any help and advice would be greatly appreciated....
Regards
Roger
A master milestone plan showing project status of 25 projects handled
by 12 PM's is being used at work.
The existing process is to have each PM update a separate MS Project
file "Master Milestone Plan" (or MMP for short). A time consuming and
unwieldy process as the same information is being entered in two
different locations by 12 PM's.
The solution seems to be to create the MMP, then on a weekly basis,
insert the latest copy of the sub projects (25 of) into the MMP.
1. Is this a good procedure?
2. What is the impact of PM's using different calendars?
3. If projects are baselined, what impact on the MMP will be made?
4. If changes are made in the MMP - what if scenarios for example, the
sub projects will be affected. How can this be managed?
Any help and advice would be greatly appreciated....
Regards
Roger