K
KTA
Hi,
We are working on large program with Master Program Schedule that has
different stream of work inserted projects. Most of the tasks/activities are
linked within their phases and have no external links. The Phases are also
not linked as most of them have different starting dates and there is no
sequencing in them.
I need to draw Network diagram and generate a Program Critical Path. When i
do so, it appears with very weird diagram that doesn't depict reality and
skip few streams of work all together.
When i choose the option, show multiple critical paths, it comes up with
almost everything is critical.
So is there any better way of doing it Or am i missing something fundamental
in terms of task(s) or phase linking.
Looking forward to hearing from experts.
thanks in advance.
Regards,
KTA
We are working on large program with Master Program Schedule that has
different stream of work inserted projects. Most of the tasks/activities are
linked within their phases and have no external links. The Phases are also
not linked as most of them have different starting dates and there is no
sequencing in them.
I need to draw Network diagram and generate a Program Critical Path. When i
do so, it appears with very weird diagram that doesn't depict reality and
skip few streams of work all together.
When i choose the option, show multiple critical paths, it comes up with
almost everything is critical.
So is there any better way of doing it Or am i missing something fundamental
in terms of task(s) or phase linking.
Looking forward to hearing from experts.
thanks in advance.
Regards,
KTA