Master Project -- Can't outdent

J

JimS

Somehow, I must have made this a master project. I'll deal with that later.
For now, though, I need to remove the redundant "0" heirarchy from the
project. I can't "outdent" the sub-heirarchies, MSP won't let me.

Do I have to copy the sub-hierarchies to a new project?

That's what I'll do for now.... Help!
 
J

Jack Dahlgren MVP

Go to Tools Menu / options / general tab and deselect the "show project
summary task" option at the lower right.
The project summary task is not actually redundant. It is pretty useful for
showing rolled up duration, work, cost etc. for the project.
I often teach people how to display it.

-Jack Dahlgren
 