Master Project Deliverables

C

Craig Smillie

HI,

I have a Master project with 11 sub-projects inserted. I've used the
Deliverables feature within each of the sub-projects, but is ther a way that
I can have overall visibility of all Deliverable from the Master Project?

In other words, say I've one deliverable in each project - I'd like in the
Workspace for the master project top be able to see them all, that way I
could keep track of the project from one screen.

Is this possible?

Many thanks

Craig
 
A

Andrew Lavinsky

I've researched this before, and believe it to be technically feasible
although I haven't done it myself.

Grab your closest SharePoint developer and tell them you want to deploy
deliverables as content types, then aggregate them into a master list, and
they should be able to figure it out - albeit with a couple of nuances on how
to get content types to work with Project Server.

Failing that, grab an SSRS developer and have them write a report against
it. That would probably be easier, but perhaps not as fun.

-A
 