T
tdbcalif
I am thinking about using a master project to consolidate approx. 10
individual plans.
I'm testing the updating process and have some questions, specifically
around dependencies:
Background:
Currently, the 10 different plans are updated and submitted to me each week.
I have created a network folder that will store the master plan and the most
recent 10 subproject plans. (Unfortunately, not everyone has access to the
network, so the 10 individual plans will be emailed to me and I will save to
the network folder)
Scenario:
Master Plan, Plan A and Plan B and Task # x in Plan B has an external
dependency on Task # y in Plan.
New Plans A and B are submitted. I overwrite the existing Plans A & B in the
network folder with the new Plans.
Task # Y in Plan B is now Task # Y + 1 due to a new task being inserted.
I open the Master plan and the external dependency link is maintained even
though the new plan # B does not have the dependency.
Question:
I set up the dependency in the master plan, but I overwrote the old Plan B
with the new Plan B, which does not have the external dependency defined in
it, so I expected the link to be lost.
How does this work?
Thanks!
Thanks
individual plans.
I'm testing the updating process and have some questions, specifically
around dependencies:
Background:
Currently, the 10 different plans are updated and submitted to me each week.
I have created a network folder that will store the master plan and the most
recent 10 subproject plans. (Unfortunately, not everyone has access to the
network, so the 10 individual plans will be emailed to me and I will save to
the network folder)
Scenario:
Master Plan, Plan A and Plan B and Task # x in Plan B has an external
dependency on Task # y in Plan.
New Plans A and B are submitted. I overwrite the existing Plans A & B in the
network folder with the new Plans.
Task # Y in Plan B is now Task # Y + 1 due to a new task being inserted.
I open the Master plan and the external dependency link is maintained even
though the new plan # B does not have the dependency.
Question:
I set up the dependency in the master plan, but I overwrote the old Plan B
with the new Plan B, which does not have the external dependency defined in
it, so I expected the link to be lost.
How does this work?
Thanks!
Thanks