(Master project)How to update changes on working hours

E

Edgar Guadamuz

I have a master project where I inserted several project files.

I'm wondering if there is a way to edit the working hours in the master
project ( for example add holidays) so that each inserted project gets its
own calendar updated.

Thks
 
J

JulieS

Hello Edgar,

You can create a new calendar in the Master Project or edit the
Standard calendar (Tools > Change Working Time). Then using the
Organizer (Tools > Organizer) copy the calendar into each subproject
file. Set each subproject file to use that calendar if necessary
(Project > Project Information).

This is *not* automatic -- if you edit the master calendar again,
you would need to repeat the process.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 