Master project only reporting on its sub projects

R

ritu

Hi

I am currently working on a 12 month resource report, I started out in
Excell but i thought i should use project being a project manager! I started
with a project containing resources on one team company target billable
hours. 2nd project with all projects they are assigned to in Feb and there
hours assigned.

They are then inserted into a master project, i then select report, workload
and resource usage, i then get a total number of hours left in the month
after all projects (which i need). However also listed are all projects
publised in project server and they show no hours.

I cant use this report for presentation, is there anyway i can can get the
report to show just February and just the subprojects in the master projects?

hope you can help
thanks
ritu
 
R

ritu

Thanks that has helped alot, and now i dont need to run a report view as i
can just print this out as it is.

Thanks again!!!!
 