T
tgreen_etc
Hello, I currently use a master project plan to manage multiple project plans
in one file. I update the master plan by choosing "Insert > Project". I
un-check the box to "link to project" since I want this file to remain
independent of the source project plans. My problem is this:
It is typical that the overall start date (when viewing at outline level
one) for a project will change at this point (this happens in about 1/3 of
the overall projects I insert). For example, I insert a project that starts
6/1/2009, but once it is inserted it will start 3/10/2009. This is due to
the fact that between 1 and 3 tasks are moved to an earlier date once the
project is inserted; in turn, every week I find myself needing to go through
the plans and manually change the dates for those tasks back. In addition,
all plans that change the start date will change to the same date (in my
case, any plan that changes always goes to 3/10/2009).
I have no idea what is going on here, please help me if you can!
in one file. I update the master plan by choosing "Insert > Project". I
un-check the box to "link to project" since I want this file to remain
independent of the source project plans. My problem is this:
It is typical that the overall start date (when viewing at outline level
one) for a project will change at this point (this happens in about 1/3 of
the overall projects I insert). For example, I insert a project that starts
6/1/2009, but once it is inserted it will start 3/10/2009. This is due to
the fact that between 1 and 3 tasks are moved to an earlier date once the
project is inserted; in turn, every week I find myself needing to go through
the plans and manually change the dates for those tasks back. In addition,
all plans that change the start date will change to the same date (in my
case, any plan that changes always goes to 3/10/2009).
I have no idea what is going on here, please help me if you can!