K
kvidy
1.
I have a big number of Sub-projects in a master project file and it takes a
lot of time to level after I open the file. I spend nearly an hour opening 45
files. Is there a better way out? I cannot split the master projects file
further because I need some consolidated information. Is there a way I can
save sub-projects with all the levelling effects so that I don't have to
level again when I open the master project file? Will opening the resource
pool file (I work on Project Pro 2003 without the Project Server) in write
mode help?
2. Is it possible to generate a Resource Usage Gantt. By that I mean, the
Resource Usage View on the left and the Gantt on the right side. I do not
want the Gantt with any task associated view. I find that all Gantt Charts
are only associated with Tasks and not resources. Can it be achieved with VBA
Code?
I have a big number of Sub-projects in a master project file and it takes a
lot of time to level after I open the file. I spend nearly an hour opening 45
files. Is there a better way out? I cannot split the master projects file
further because I need some consolidated information. Is there a way I can
save sub-projects with all the levelling effects so that I don't have to
level again when I open the master project file? Will opening the resource
pool file (I work on Project Pro 2003 without the Project Server) in write
mode help?
2. Is it possible to generate a Resource Usage Gantt. By that I mean, the
Resource Usage View on the left and the Gantt on the right side. I do not
want the Gantt with any task associated view. I find that all Gantt Charts
are only associated with Tasks and not resources. Can it be achieved with VBA
Code?