Hello
I have read with great interest a lot of yours questions and answers on
Master Project but I have not found answer for my issue.
We use EPM (MS Project, PWA for time key in), managed periods.
I have created a master project XXXX, including
Project P1
Resource R1
Resource R2, etc.
Project P2
Resource R1
Resource R2, etc.
When I open my master project in Project with the "Load assignment .."
option checked, I see in the "Resource usage" view assignement of R1, R2 in
P1, P2 but also P3, P4 (projects of other PM).
When I open my master project in Project with the "Load assignment .."
option unchecked, I see in the "Resource usage" only assignement of P1 (first
project inserted in the master project).
How can I see planned figures (Work, Actuals work, etc) of resources for my
own projects only?
THANKS
I have read with great interest a lot of yours questions and answers on
Master Project but I have not found answer for my issue.
We use EPM (MS Project, PWA for time key in), managed periods.
I have created a master project XXXX, including
Project P1
Resource R1
Resource R2, etc.
Project P2
Resource R1
Resource R2, etc.
When I open my master project in Project with the "Load assignment .."
option checked, I see in the "Resource usage" view assignement of R1, R2 in
P1, P2 but also P3, P4 (projects of other PM).
When I open my master project in Project with the "Load assignment .."
option unchecked, I see in the "Resource usage" only assignement of P1 (first
project inserted in the master project).
How can I see planned figures (Work, Actuals work, etc) of resources for my
own projects only?
THANKS