C L Haddad
Have an MS Project 'Master' Plan that includes subprojects imbedded within
it. These subprojects comme in by pointing to a separate subproject file.
Both the master and the subprojects use the same resource list. Reources are
assigned in the subproject tasks and in the higher lever master plan tasks.
The % complete is also assigned in subproject tasks. When I bring in the
subprojects, the resources and the % complete do not appear, but they are
there in the separate subproject file. Can anyone help me identify what I
may be doing wrong?
it. These subprojects comme in by pointing to a separate subproject file.
Both the master and the subprojects use the same resource list. Reources are
assigned in the subproject tasks and in the higher lever master plan tasks.
The % complete is also assigned in subproject tasks. When I bring in the
subprojects, the resources and the % complete do not appear, but they are
there in the separate subproject file. Can anyone help me identify what I
may be doing wrong?