M
Margy Garland
I am using MSP 2002 to create a Master Project. I have 12 subprojects. The first 11 inserted fine and I have had no problems with their alignment.
However, when inserting the 12th project, it tries to be subordinate to the 11th project and not the central controlling project. All of the other subprojects I have inserted have gone in subordinate to the contral controlling project without any problem. I can't figure out why this is happening and I don't know where else to look
I have looked at the source of the 12th project and nothing appears to be unusual about its alignment. Its first task line (which is really the project's highest level summary line) is aligned all the way to the left like one would expect. To insert a subproject, I place my insertion point in the appropriate row in the Indicators Box. Then do the insert project. Any clue where I should look to correct this situation
Thank you for your help
Margy Garland
However, when inserting the 12th project, it tries to be subordinate to the 11th project and not the central controlling project. All of the other subprojects I have inserted have gone in subordinate to the contral controlling project without any problem. I can't figure out why this is happening and I don't know where else to look
I have looked at the source of the 12th project and nothing appears to be unusual about its alignment. Its first task line (which is really the project's highest level summary line) is aligned all the way to the left like one would expect. To insert a subproject, I place my insertion point in the appropriate row in the Indicators Box. Then do the insert project. Any clue where I should look to correct this situation
Thank you for your help
Margy Garland