R
Rob
We upgraded from Project 2000 hoping that we could get away from
building a Master to level 150+ shared resources involving 100+
projects at any given time, while planning projects as far out as 3
years. We use "Finish No Later Than" dates on the projects to allow
flexability in the actual start dates while looking at all the project
required dates.
After installing 2003 we could not find a way to accomplish this with
out building a Master. After doing that I can see why they don't
advise to build masters.
1) Is there another way to level all resources and all projects
without a Master?
2) To open the master takes 5-6 minutes to open and 7-8 minutes to
save.
3) Resource availability and "work" does not show up in the Enterprise
Global Rsource Pool,while all projects are using resources from this
pool. Is this the way is works? We also cannot get the resource
availability to show on Web Acess for any dates now or in the future.
4) Can you remane project files on the server?
building a Master to level 150+ shared resources involving 100+
projects at any given time, while planning projects as far out as 3
years. We use "Finish No Later Than" dates on the projects to allow
flexability in the actual start dates while looking at all the project
required dates.
After installing 2003 we could not find a way to accomplish this with
out building a Master. After doing that I can see why they don't
advise to build masters.
1) Is there another way to level all resources and all projects
without a Master?
2) To open the master takes 5-6 minutes to open and 7-8 minutes to
save.
3) Resource availability and "work" does not show up in the Enterprise
Global Rsource Pool,while all projects are using resources from this
pool. Is this the way is works? We also cannot get the resource
availability to show on Web Acess for any dates now or in the future.
4) Can you remane project files on the server?