master projects not displaying tasks on PWA

W

WSH

Hello

I have a master project with lots of sub-projects inserted in. In the
subprojects, if you expand it, lots of little tasks are displayed.

However on the PWA, the master project is shown with all my sub projects in,
but when I try expanding by clicking on the plus sign of each subproject, all
the little tasks are not displayed. I went on the view options to make sure
all outline levels are shown. Have I done something wrong?

Thanks for helping
 
D

Dale Howard [MVP]

WSH --

You did nothing wrong. When you click on a master project in the Project
Center page, the detailed Project view only shows the subprojects. It does
not show the tasks in each subproject. Sorry.
 
T

Thom.Moore

Will this be fixed in the 2007 version?

Dale Howard said:
WSH --

You did nothing wrong. When you click on a master project in the Project
Center page, the detailed Project view only shows the subprojects. It does
not show the tasks in each subproject. Sorry.
 