Hello,

i added all of our projects in a master project to solve the resource
conflicts. After capacity leveling and some manual changes i save my master
project and all changed embedded projects. Till now, everything is OK.

If the ressources enter the working time in the updated task, the task
updates are sent to the project managers AND to me!

How can i avoid to get task updates from all projects?

Thanks

Frank
 