M
Marie
When I open the master schedule it automatically opens
the subproject - as it should. However, I note that a
number of tasks appear multiple times straight under each
other - one task has the correct predecessors /
successors but the others have a predecessor back to the
one above and they appear in grey text not black. I have
deleted them but note that other appear throughout the
schedule each time I open it.
Does anybody know what they are or how they are caused?
and what I can do to prevent them from happening? Is
there a 'version control' available as part of Project
2000?
the subproject - as it should. However, I note that a
number of tasks appear multiple times straight under each
other - one task has the correct predecessors /
successors but the others have a predecessor back to the
one above and they appear in grey text not black. I have
deleted them but note that other appear throughout the
schedule each time I open it.
Does anybody know what they are or how they are caused?
and what I can do to prevent them from happening? Is
there a 'version control' available as part of Project
2000?