M
MikeF
I need the experts help! I'm using project standard 03 and am trying to
create a mater schedule to include 50 sub-projects using a standard template.
Each project has a summary task that roll-ups earned value and progress info
as of a certain status date. When I create a master project schedule and link
the sub-projects into it, it creates an add'l summary task that calculates EV
metrics as of the current date and not the status date for each individual
project. Is there a solution in Project 03? Or do I need Project Server or
Project 2007 Professional? I simply need to create a read-only link from the
master to each sub-project and have it automatically update the master every
time a status update is applied to each sub-project without needing to update
baseline or have extraneous summary levels? Any thoughts?
create a mater schedule to include 50 sub-projects using a standard template.
Each project has a summary task that roll-ups earned value and progress info
as of a certain status date. When I create a master project schedule and link
the sub-projects into it, it creates an add'l summary task that calculates EV
metrics as of the current date and not the status date for each individual
project. Is there a solution in Project 03? Or do I need Project Server or
Project 2007 Professional? I simply need to create a read-only link from the
master to each sub-project and have it automatically update the master every
time a status update is applied to each sub-project without needing to update
baseline or have extraneous summary levels? Any thoughts?