Master Schedule View or Report from Server

H

HCLIFF

We currently have a schedule importing 20 projects into a master schedule so
our Dir can get overall view of his area. To avoid having to open 20 project
everytime someone looks at this schedule, we would like a master project view
or report that allows the Dir to select just his projects from all the
projects in EPM. Any ideas how this can be accomplished?

Thanks
 
M

Marc Soester [MVP]

Hi HCLIFF,

Are you useing Proejct Server 2007? If so you can publish master projects
which can be viewed in the Project Center of PWA.

hope this helps
 
M

Marc Soester [MVP]

Hi HCLIFF,

sorry to say, but you cant publish master projects in 2003, this would
double up your numbers in PWA.

With a bit of luck the next version may be out by 09 :)

--
Marc Soester [MVP]
National Manager: EPM
http://marcsoester.blogspot.com
 
M

Marc Soester [MVP]

Hi HCLIFF,

sorry to say, but you cant publish master projects in 2003, this would
double up your numbers in PWA.

With a bit of luck the next version may be out by 09 :)
--
Marc Soester [MVP]
National Manager: EPM
http://marcsoester.blogspot.com
 