J
JanK
Using Project 2000, SR/1, (NOT using Project Central)
I'm going to be setting up a Master Schedule with several (10 - 15) sub-projects in separate files. A separate file will be the Resource Pool used by the sub-projects. A co-worker of mine *thinks* there is some sort of bug in MS Project 2000 when using a common Resource Pool.
Is anyone aware of this? Other possible "gotchas" using a common resource pool/ master & subprojects that I should know about
Thank you in advance
Jan K, PMP
I'm going to be setting up a Master Schedule with several (10 - 15) sub-projects in separate files. A separate file will be the Resource Pool used by the sub-projects. A co-worker of mine *thinks* there is some sort of bug in MS Project 2000 when using a common Resource Pool.
Is anyone aware of this? Other possible "gotchas" using a common resource pool/ master & subprojects that I should know about
Thank you in advance
Jan K, PMP