hello,
i would like to explain my problem with masterplan before I loose my mind!
I have 2 projects (project A and project B)in which my resources has
inserted their work hours since jenuary.
Last week my boss decided to insert these 2 project as subproject of a
masterplan. this master plan has new task liked to tasks of project A and
Project B.
now what i did: i open a new project (masterplan) and I insert project A
and B, then i create link betweek task. and it was working good. I saved and
i published the masterplan.
today I open the master plan and the icon of the sub project was in read "
this insert project is not valid, a project can be inserted only once in a
consolidated project"...what does it means?
I don't see all links I've made last week!! what i have to do?
do you have any idea of this problem? can you help me?
i would like to explain my problem with masterplan before I loose my mind!
I have 2 projects (project A and project B)in which my resources has
inserted their work hours since jenuary.
Last week my boss decided to insert these 2 project as subproject of a
masterplan. this master plan has new task liked to tasks of project A and
Project B.
now what i did: i open a new project (masterplan) and I insert project A
and B, then i create link betweek task. and it was working good. I saved and
i published the masterplan.
today I open the master plan and the icon of the sub project was in read "
this insert project is not valid, a project can be inserted only once in a
consolidated project"...what does it means?
I don't see all links I've made last week!! what i have to do?
do you have any idea of this problem? can you help me?