Is it possible to assign a task a batch of type material i.e. 100 widgets and
depending on the amount of widgets used in any given day, a resource will
enter the actual amount and the system will do the other calculations,
variances etc.? Similar to the Work field and Actual field for resources. The
idea is to track the actual amount of a material used and the associated
costs within a project.
Can the actual data be entered in PWA or must it be entered directly in the
project plan?

thx

Paul
 