D
Debbie P
Our Material Cost View is not acting consistently and am wondering if anyone
knows what the reason and/or fix might be.
In some instances it is working as desired where once the material resource
is assigned to a task you must enter the units into Actual Work then Actual
Cost is calculated. Entering directly into Actual Cost is blocked.
In other instances it will block from allowing input into Actual Cost on the
first input column then will allow it after that. If data is input into the
Actual Cost field Actual Work is not calculated and the 2 become out of sync.
In even other instances it allows input into Actual Cost on the first try.
The problem does not seem to be project specific either. Sometimes it works
OK on a project and other times it doesn't. I have not been able to identify
any commonality in occurance.
Thanks,
Debbie
knows what the reason and/or fix might be.
In some instances it is working as desired where once the material resource
is assigned to a task you must enter the units into Actual Work then Actual
Cost is calculated. Entering directly into Actual Cost is blocked.
In other instances it will block from allowing input into Actual Cost on the
first input column then will allow it after that. If data is input into the
Actual Cost field Actual Work is not calculated and the 2 become out of sync.
In even other instances it allows input into Actual Cost on the first try.
The problem does not seem to be project specific either. Sometimes it works
OK on a project and other times it doesn't. I have not been able to identify
any commonality in occurance.
Thanks,
Debbie