Material Costs in PWA

M

MAT

Hallo
I want to see the cost of the material in a project in PWA.
In MS Project we have a standart view "Ressource: usage". Hier i can seethe
cost of all ressources (material too).
But in PWA we have a standart view Resource:Cost. Hier i cant see the
materialcost. I know that for the materials there is no account. but it must
be possible to see the total cost of each Material in PWA..
Thx..
 
M

Michelle D.

Hello Mat,

Resource costs, both Material and Work (resources) are not available in any
of the resource views PWA. The only cost information in PWA are costs
associated with project tasks. This is design intent, in an effort to keep
proprietary information, such as resources rates private to those with access
to the actual project files in MS Project Professional.
 