Material Costs

M

markdanielmaltby

Please open the attached project. I would like to understand why the
remaining cost is £5 and not £10 on task - spread. There is 5 units of
a resource of type material at a cost of £5. The actual duration is 4
and remaining duration is 2. It just doesn't add up.

Thanks for any help in advance.


+-------------------------------------------------------------------+
|Filename: 5211.zip |
|Download: http://forums.techarena.in/attachment.php?attachmentid=7306|
+-------------------------------------------------------------------+
 
J

JulieS

Hello markdanielmaltby,

Your remaining two days of duration only have .5 unit of resource b
assigned to each day. Look at the Task Usage view to see your units
per day. Days 1-4 all show 1 unit per day, days 5 & 6 each show .5
units.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top