J
Jeff Hutchinson, PMP
Hi -
I am having trouble with accurate reporting when adding hardware
materials to my plan.
I am running a $266K project that is where duration % complete is 34%
and work % complete is 37% and I've actually only spent $77K. Sounds
pretty good right.
$100K of the $266K is for 4 servers and the software that is required.
I have added this $100K material resource to the resource pool and
assigned it to the "Order Hardware" activity in my project schedule.
When the "Order Hardware" activity is 0% complete, my CPI is around
1.2 and my SPI is around 1.09. Sounds great right.
Well we just ordered the server last friday so I want to update it to
100% complete. Only thing is then my project actual cost has just
increased by $100K and now my CPI is .5.
I am very particular in the way that I report project performance. I
use the Earned Value Management (EVM) methodology....reporting BAC,
AC, Planned % Complete, Actual $ Complete, PV, EV, SV and CV.
I want to show that I have purchased this $100K item but I don't want
it to show that I have grossly overbudget either.
Any ideas?
Thank you,
Jeff Hutchinson, PMP
I am having trouble with accurate reporting when adding hardware
materials to my plan.
I am running a $266K project that is where duration % complete is 34%
and work % complete is 37% and I've actually only spent $77K. Sounds
pretty good right.
$100K of the $266K is for 4 servers and the software that is required.
I have added this $100K material resource to the resource pool and
assigned it to the "Order Hardware" activity in my project schedule.
When the "Order Hardware" activity is 0% complete, my CPI is around
1.2 and my SPI is around 1.09. Sounds great right.
Well we just ordered the server last friday so I want to update it to
100% complete. Only thing is then my project actual cost has just
increased by $100K and now my CPI is .5.
I am very particular in the way that I report project performance. I
use the Earned Value Management (EVM) methodology....reporting BAC,
AC, Planned % Complete, Actual $ Complete, PV, EV, SV and CV.
I want to show that I have purchased this $100K item but I don't want
it to show that I have grossly overbudget either.
Any ideas?
Thank you,
Jeff Hutchinson, PMP