M
Mike F
One can modify a resource's Max Units for an entire project rather than using
Assignment Units per task. However, Project states that this is for
"modeling" purposes only and will not be saved when the project is
re-opended. Max Units can only be changed in the Enterprise Resource Pool for
the resource which makes it a global change for all projects that this
resource is on. Is this correct?
How can I change resource's Max Units per project? Assignment Units still
allow for tasks to be scheduled on top of each other up to the resource's max
units per day. I only want a resource to be available for project work 60% of
the time.
My problem is that I am using a master project with inserted projects and it
is scheduling resources to their Max Unit of 8hr per day. This does not allow
for the resource's non-project time to be factored into this master when
scheduled and leveled. Therefore, the finish dates are not reflecting reality.
Assignment Units per task. However, Project states that this is for
"modeling" purposes only and will not be saved when the project is
re-opended. Max Units can only be changed in the Enterprise Resource Pool for
the resource which makes it a global change for all projects that this
resource is on. Is this correct?
How can I change resource's Max Units per project? Assignment Units still
allow for tasks to be scheduled on top of each other up to the resource's max
units per day. I only want a resource to be available for project work 60% of
the time.
My problem is that I am using a master project with inserted projects and it
is scheduling resources to their Max Unit of 8hr per day. This does not allow
for the resource's non-project time to be factored into this master when
scheduled and leveled. Therefore, the finish dates are not reflecting reality.