R
ronjon
i'm working on custom reports for my organisation in MS Project Server
and experience difficulties with the max units we have assigned to our
resources.
example:
i have a resource who is available for 8hours per day, but due to the
type of work i can only assign him for 90% (7.2h) per day on a project,
so i set his Max Units to 90%, so far so good
Now i need a report (msp_portfolio_analyzer) where i can see (per day or
week):
the work the resource had done (Work field)
his capacity (Capacity field) - this should be 7.2h per day
his availability (before the max units) - this should be 8h per day
in the Fieldlists i can nowhere find max units or some other Field with
the availability. I tried also looking for a max units field to use in
an MDX query but can't find this anywhere.
Which field to use or is there some other way around this problem?
and experience difficulties with the max units we have assigned to our
resources.
example:
i have a resource who is available for 8hours per day, but due to the
type of work i can only assign him for 90% (7.2h) per day on a project,
so i set his Max Units to 90%, so far so good
Now i need a report (msp_portfolio_analyzer) where i can see (per day or
week):
the work the resource had done (Work field)
his capacity (Capacity field) - this should be 7.2h per day
his availability (before the max units) - this should be 8h per day
in the Fieldlists i can nowhere find max units or some other Field with
the availability. I tried also looking for a max units field to use in
an MDX query but can't find this anywhere.
Which field to use or is there some other way around this problem?