Max Units on resource sheet not matching Units on Gantt...

L

Larry

I've created an enterprise project template where all my generic resources
have 75% max units, but when i look at the gantt they show as 100%.

When i replace that resource with another from the enterprise team builder
or replace with another generic the 75% displays on the gantt as expected.

Any ideas?

thx
 
D

Dale Howard [MVP]

Larry --

When you assigned the Generic resources to tasks, did you assign them at 75%
Units or 100% Units? It sounds like the latter. Let us know.
 
L

Larry

Hi Dale,

to answer your question, i assigned all generic resources on this template
to 75%.

so when i open a new file when working on my server, and select this
template the gantt appears showing all resources at 100%. but when i switch
to the resource sheet it shows resources at 75% that i established when i
initially imported. this template has always exhibited this behaviour. i
might try another template to rule out the fact that this one may have become
corrupted. in addition i've established all resouces in my enterprise pool
to 75%

thanks again
 
G

Gary L. Chefetz [MVP]

Larry:

Just to be clear, the Max Units on the resource sheet determines the default
units for new assignments. The Gantt chart indicates the units at which the
assignment was made for the specific tasks.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top