S
Session
Hi. I'm looking to assign a resource to multiple concurent tasks of
different durations. What I would like is for leveling to spread the
resource's unit usage equally across the tasks to cover an 8hr schedule every
working day: meaning that if he is working on 3 tasks at the same time, he
will be assigned at 33% for each, and once one of the tasks is over, than
he'll be assigned 50% for each of the remaining 2. So the unit usage won't
be constant for an entire task. Is that even possible with Project 2007, is
it possible in code?
Thanks,
Session
different durations. What I would like is for leveling to spread the
resource's unit usage equally across the tasks to cover an 8hr schedule every
working day: meaning that if he is working on 3 tasks at the same time, he
will be assigned at 33% for each, and once one of the tasks is over, than
he'll be assigned 50% for each of the remaining 2. So the unit usage won't
be constant for an entire task. Is that even possible with Project 2007, is
it possible in code?
Thanks,
Session