Maximum hours per day in Admin Projects

B

BECalvert

My agency has three base calendars for work resources:

Standard - 5-8 hour days per week,
9-80 Group 1 - 8-9’s and an 8 with every other Friday off, and
9-80 Group 2 - 8-9’s and an 8 with every other Friday off, the Friday off
being Group 1’s working Friday

In Project Web Access, Tasks, after clicking “Notify your manager of time
you will not be available for project work†the Administrative Project Tasks
to which I have been assigned appear. When I enter 9h in the appropriate
date/task box, an error message appears: “The value entered exceeds the
maximum allowed value for work hours per day.â€

The Admin Project Calendar and resource calendar provides a 9h day, the
Calendar tab of the Admin Project’s Options has been changed to make a 9h day
/45 hour week standard.

I have used 0, 24 and 15 as the limit on the maximum hours that can be
entered setting on the Customize Project Web Access page
Time Period Settings section, and the problem still persists. There never
was a problem entering more than 8 hours in the actuals, this is an issue
with using the
Admin Project to "Notify your manager of time you will not be available for
project work"

1. What do I need to change to allow resources to enter 9h when reporting
Admin Time via “Notify your manager of time you will not be available for
project work?â€
 