Maximum hours per day when notifying manager of unavailability

D

Dredman

In our MS Project 2003 server we are unable to enter more than 8 hours when
notifying our manager about time we will be unavailable to work on projects.
Is there a way to change this? Our schedules vary because of flexible
reporting; e.g., working 4 tens or 9 by 80.
 
M

Marc Soester

Hi Dredman,

You can decide how many hours you can report per day within the admin
section on PWA
Go to PWA > Admin > Customise Project Web Access.
You will find a section called:
- Maximum number of hours that can be entered per day for a single task
(enter '0' for no limit): -
Enter the manximum amount of hours ( or 0 for no limitation )
hope this helps
 
D

Dredman

Marc,

Thanks for you reply; however, that doesn't seem to be the problem. The max
hours was set at 10, but still allow only 8 hours to be entered. I changed it
to 0, but that made no difference. It still allows a max of only 8 hours. Any
other thoughts??

Don
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top