Maximum Work

S

stuart block

Can somebody advise on how I can set a maximium work limit per day.

I have set a maximium resource limit which cumulative comes to say 12 across
multiple resources.

But I only have 10 desks, how can project level against this and move task
to best optimise usage for the 10 desks.

Thanks in advance.
 
J

Jan De Messemaeker

Hi,

First, one thing I shoudld warn about.
Project doesn't OPTIMIZE anything. It xcalculates dates frm your input but
do not look for a OPTIMIZATION routine.
This being said, the following will help you:
To each task using a person also add the resource "Desk" - after setting
effort driven off;
Now set max units for Desk to 10
Level with the opytion "Levelinbg can adjust individual assignments.." off

HTH


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
S

stuart block

Thanks Jan,

I'd forgotten about this. Its been a while since I used project.

Regards
Stuart
 