M
Michele
I have a project scheduled from the end date.
I have a number of tasks that generate a critical path.
I create another task called, just for example, "y", with no relationship
with any of the other tasks.
Even if this behaviour is different(and rightly logic) in a project
scheduled from the start date, i can accept the fact that, no matter what
constraint i give to task "y" between the two possibilities "As soon as
possible" or "As late as possible", the task "y" is not considered critical
by microsoft project.(The duration of the project is anyway longer than the
duration of the single "y" task)
My problem is:
If i set for the task "y" an actual start date the task "y" becomes critical
no matter what actual start date or what constraint betwenn "As soon as
possible" or "As late as possible" i give it. (I put an actual start date in
the possible range of the critical path, not making it end after the end date
of the project).
It's for me logic that early and late start dates are fixed by the Actual
Start date but i really can't undertsand why the early and late finish dates
are always the same, no matter if i give the task "As soon as possible" or
"As late as possible" constraint, causing the task "Y" to be always critical.
If things worked like they work in a project scheduled from the start date
and about what i wrote in one of my previous question(Object: "Total slack
not correct", Date: 11/13/2005), i would expect that if i gave "As late as
possible" constraint to task "y" than project would force the early and late
finish dates to be the same(like it, infact, does) but if i gave "As soon as
possible" constraint to task "y" than project wouldn't force the early and
late
finish dates to be the same(like he, instead, does) or i even would expect
the opposite.
Anyway, again and more than how it happens in a project scheduled from the
start date i can't understand why project indicates me that a task is
critical when the fact that i delay it won't have any consequences on the end
date of the project or on any other aspect of the project.
What i mean is that if, at the beginning, i scheduled the task "y" to start
"As soon as possible" but , in facts, the task "y" actually starts later i
would expect that project told me that the total slack amount of "y" was not
0 and the same if the initial constraint of "y" was "As late as possible",
that is in both cases my task "y" is not absolutely critical, i can delay it
untill it reaches the end date of the project.
Thanks in advice for helping me in understanding.
Michele
I have a number of tasks that generate a critical path.
I create another task called, just for example, "y", with no relationship
with any of the other tasks.
Even if this behaviour is different(and rightly logic) in a project
scheduled from the start date, i can accept the fact that, no matter what
constraint i give to task "y" between the two possibilities "As soon as
possible" or "As late as possible", the task "y" is not considered critical
by microsoft project.(The duration of the project is anyway longer than the
duration of the single "y" task)
My problem is:
If i set for the task "y" an actual start date the task "y" becomes critical
no matter what actual start date or what constraint betwenn "As soon as
possible" or "As late as possible" i give it. (I put an actual start date in
the possible range of the critical path, not making it end after the end date
of the project).
It's for me logic that early and late start dates are fixed by the Actual
Start date but i really can't undertsand why the early and late finish dates
are always the same, no matter if i give the task "As soon as possible" or
"As late as possible" constraint, causing the task "Y" to be always critical.
If things worked like they work in a project scheduled from the start date
and about what i wrote in one of my previous question(Object: "Total slack
not correct", Date: 11/13/2005), i would expect that if i gave "As late as
possible" constraint to task "y" than project would force the early and late
finish dates to be the same(like it, infact, does) but if i gave "As soon as
possible" constraint to task "y" than project wouldn't force the early and
late
finish dates to be the same(like he, instead, does) or i even would expect
the opposite.
Anyway, again and more than how it happens in a project scheduled from the
start date i can't understand why project indicates me that a task is
critical when the fact that i delay it won't have any consequences on the end
date of the project or on any other aspect of the project.
What i mean is that if, at the beginning, i scheduled the task "y" to start
"As soon as possible" but , in facts, the task "y" actually starts later i
would expect that project told me that the total slack amount of "y" was not
0 and the same if the initial constraint of "y" was "As late as possible",
that is in both cases my task "y" is not absolutely critical, i can delay it
untill it reaches the end date of the project.
Thanks in advice for helping me in understanding.
Michele