K
K Major
I have a 2 hour (fixed duration/non-effort driven) meeting that will be
attended by 5 people. All 5 are part-time on my project (50% in the resource
sheet), so I have them each for four hours a day.
Since they are 50% on my project (instead of 100%), they only get allotted 1
hour of work for the meeting when it should be 2 hours of work. My only
solution to this is to bump them up to 100% on the task's resource assignment
- however, this immediately over-allocates them EVEN if this is the only
actvity for the day (i.e. I have them for 4 hours and am only using 2 of
those 4 hours). Plus, this type of over-allocation cannot be resolved (i.e.
it stays RED) because they are above their assignment units of 50% in the
resource sheet.
Do I have any options?
Help!
attended by 5 people. All 5 are part-time on my project (50% in the resource
sheet), so I have them each for four hours a day.
Since they are 50% on my project (instead of 100%), they only get allotted 1
hour of work for the meeting when it should be 2 hours of work. My only
solution to this is to bump them up to 100% on the task's resource assignment
- however, this immediately over-allocates them EVEN if this is the only
actvity for the day (i.e. I have them for 4 hours and am only using 2 of
those 4 hours). Plus, this type of over-allocation cannot be resolved (i.e.
it stays RED) because they are above their assignment units of 50% in the
resource sheet.
Do I have any options?
Help!