T
Tricky
I have merged two projects in MSP 2003 (using window/new window) that contain
the same resource names, however MSP is not giving me an ’all up’ resource
number based on the sum of both projects.
What it does give me is the resource graph twice based on the individaul
data for each project, but not a combined total/graph.
Can anyone tell me if it is possible to get a totalised graph, and if so how?
Also when i click in a specific activity row i get the total resource graph
for that project, and not just that particular task. What do i need to change
in the set up to get MSP to show that tasks resource graph.
thanks
the same resource names, however MSP is not giving me an ’all up’ resource
number based on the sum of both projects.
What it does give me is the resource graph twice based on the individaul
data for each project, but not a combined total/graph.
Can anyone tell me if it is possible to get a totalised graph, and if so how?
Also when i click in a specific activity row i get the total resource graph
for that project, and not just that particular task. What do i need to change
in the set up to get MSP to show that tasks resource graph.
thanks