G
Girija
Hello,
I have planned a project and updations are happening . But suddenly I see a
message popping up and mentioning to make a task As soon as possible as it
cannot be completed. Now it would be nice if someone can help me in
understaning this!
Does it mean that the predecessor task might have delayed by the resource so
the current is impacted and is supposed to change ?
Also if this so what should be done?
Thanks
Girija
I have planned a project and updations are happening . But suddenly I see a
message popping up and mentioning to make a task As soon as possible as it
cannot be completed. Now it would be nice if someone can help me in
understaning this!
Does it mean that the predecessor task might have delayed by the resource so
the current is impacted and is supposed to change ?
Also if this so what should be done?
Thanks
Girija